Roswell Cluster Improvements

 

 

 

 

 

Roswell High School

Major building renovation and modification of existing building and site improvements which may include the following work:

• Replace as needed marker/tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replace as needed fixed furniture such as cabinets, countertops, blinds and fixed seating.

• Replacement of floor finishes as needed.

• Painting as necessary.

• Replace domestic water heaters as required.

• Update building’s HVAC system and controls as required.

• Replace emergency generator.

• Update intercom and sound systems required.

• Replace fire alarm system and devices as required.

• Update security system as required.

• Revise electrical service to kitchen and serving line equipment as needed.

• Reconfigure kitchen and dining room for additional serving lines.

• Replace kitchen’s cooler and freezer.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Replace sidewalks as necessary.

Start Design: Complete

Start Construction:  Summer 2014

Final Completion: Fall 2015

 

Crabapple Middle School

Major building renovation and modification of existing building and site improvements which may include the following work: (Note:  The project scope as shown below has been reduced in anticipation that this school may be replaced when addition captial funds become available)

• Patch and repair of exterior walls.

• Replacement and/or repair of selected doors, windows and hardware.

• Replace as needed marker/ tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replace as needed fixed furniture such as cabinets, countertops, blinds and fixed seating.

• Replacement of floor finishes as needed.

• Provide painting as needed.

• Replace and/or refinish gymnasium wood flooring.

• Replace and/or repair terrazzo flooring as required.

• Replace acoustical ceiling grid and tile as required.

• Replace and/or repair plumbing fixtures as required.

• Update building’s HVAC system and controls as required.

• Provide exhaust system for art room kilns.

• Replace selected light fixtures in ceiling grid.

• Update intercom and sound systems as required.

• Update fire alarm system as required.

• Update security system as required.

• Reconfigure kitchen and relocate serving lines.

• Replace electrical service to selected kitchen equipment.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Replace and/or repair sidewalks as necessary.

• Repair and/or replace tennis courts surface.

Start Design: Complete (Reduced Scope)

Start Construction: In Process (Reduced Scope)

Final Completion: Fall 2015 (Reduced Scope)

 

Elkins Pointe Middle School

Classroom addition to increase capacity by thirteen (13) instructional units. (Classroom Addition has been deleted from this program)

Renovation and modification of existing buildings and site improvements which may include the following:

• Patch and repair exterior walls.

• Replacement of floor finishes as needed.

• Painting as needed.

• Repair metal roofing as necessary.

• Update building’s HVAC exhaust system as required.

• Replace selected light fixtures in media center.

• Update fire alarm system in the gymnasium as required.

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: Summer 2016

 

Hembree Springs Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement of floor finishes as needed.

• Painting as needed.

• Replace gymnasium flooring surface

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: Summer 2016

 

Mimosa Elementary School 

Major building renovation and modification of existing building and site improvements which may include the following work:

• Replacement and/or repair of selected doors, windows and hardware.

• Replace as needed marker/tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replacement of floor finishes as needed.

• Replace acoustical ceiling grid and tile as required.

• Replace and/or repair plumbing fixtures as required.

• Update building’s HVAC system and controls as required.

• Replace kitchen exhaust hood and fans.

• Update building’s electrical systems as required.

• Replace selected light fixtures in ceiling grid.

• Update intercom and sound systems as required.

• Replace gymnasium flooring surface. (Note 1)

• Update building’s emergency power system.

• Revise electrical service to kitchen and serving line equipment as needed.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: Fall 2017

 

Mountain Park Elementary School

Major building renovation and modification of existing building and site improvements which may include the following work:

• Replacement and/or repair of selected doors, windows and hardware.

• Modify administration and main entrance for security.

• Replace as needed marker/ tack boards, toilet accessories, toilet partitions and shelving.

• Replace acoustical ceiling grid and tile as required.

• Replace floor coverings as needed.

• Provide painting as necessary.

• Replace gymnasium flooring surface. (Note 1)

• Replace roofing.

• Replace and/or repair plumbing fixtures as required.

• Replace water heater and pumps.

• Update building’s HVAC system and controls as required.

• Replace kitchen exhaust hood and fans.

• Update building’s electrical systems as required.

• Replace selected light fixtures in ceiling grid.

• Update PA system as required.

• Update building’s fire alarm system.

• Replace and/or repair domestic water piping as required.

• Revise electrical service to kitchen and serving line equipment as needed.

• Reconfigure kitchen and dining room for relocation of serving lines.

Start Design: In process

Start Construction: Summer 2015

Final Completion: Summer 2016

 

Roswell North Elementary School

Major building renovation and modification of existing building and site improvements which may include the following work:

• Replacement and/or repair of selected doors, windows and hardware.

• Replace acoustical ceiling grid and tile as required.

• Replace as needed marker/tack boards, toilet accessories, toilet partitions and shelving.

• Replace floor finishes as needed.

• Replace gymnasium flooring surface. (Note 1)

• Painting as necessary.

• Replace roofing.

• Replace and/or repair domestic water piping and plumbing fixtures as required.

• Update building’s HVAC system and controls Update building’s electrical systems as required.

• Replace selected light fixtures in ceiling grid.

• Replace emergency generator.

• Update intercom and sound systems as required.

• Update fire alarm system as required.

• Update security system as required.

• Upgrade elevator controls.

• Replace and/or refinish stage flooring.

• Replace kitchen exhaust hood and fans.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

Start Design: In Process

Start Construction: Summer 2016

Final Completion: Summer 2017

 

Sweet Apple Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement of floor finishes as needed.

• Replace gymnasium flooring surface (Note 1)

• Provide painting as needed.

• Replace electric water heaters.

• Provide fly fan at kitchen’s entrance.

• Revise electrical service to kitchen and serving line equipment as needed.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

Start Design: In Process

Start Construction:  Summer 2016

Final Completion: No Later Than Fall 2017

 

* Additional work at each campus may also include the following improvements as needed: furniture and equipment replacement, visitor identification equipment, access control upgrades and surveillance equipment. Other improvements associated with the integration of system wide technology standards, educational specifications and design requirements may also be included per Fulton County Schools’ Board policy.

** Note 1 - Floor covering replacements for elementary school gymnasium is complete.

***Note 2 – Elementary school play equipment replacement  is presently under construction.