Milton Cluster Improvements

 

 

 

 

Milton High School

Renovation and modification of existing building which may include the following:

• Replacement of floor finishes as needed.

• Repair metal roofing.

• Replace controls on elevators.

 

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Summer 2017

 

Hopewell Middle School

    Classroom addition to increase school capacity by thirteen (13) instructional units.  

    Renovation and modification of existing building and site improvements which may include the following:

• Repair, resurface and restripe parking lots as required.

• Additional parking

    • Relocate tennis courts

 

Start Design: Complete

Start Construction: In Progress

Final Completion: Fall 2016

 

Northwestern Middle School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement of floor finishes as needed.

• Painting as needed.

• Replace domestic water heaters.

• Update intercom and sound systems as required.

• Update fire alarm system as required.

• Update security system as required.

• Provide fly fan at kitchen’s entrance door.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots as required.

• Repair and/or resurface running track.

 

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Fall 2017

 

Alpharetta Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement and/or repair of selected doors, windows and hardware.

• Replace as needed marker and tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replacement of floor finishes as required.

• Painting as needed.

• Replace gymnasium flooring surface.

• Replace and/or refinish stage wood flooring.

• Replace and/or repair ceramic wall finish as required.

• Replace and/or repair ceramic and quarry floor tile as required.

• Replace acoustical ceiling grid and tile as required.

• Repair and/or replace roofing.

• Replace and/or repair domestic water piping, sanitary sewer and plumbing fixtures as required.

• Update building’s HVAC system and controls as required.

• Upgrade fire protection sprinkler system as required.

• Update building’s electrical systems as required.

• Replace selected light fixtures in ceiling grid.

• Replace emergency generator.

• Upgrade kitchen electrical and floor finishes as needed.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Replace and/or repair perimeter fencing around site.

• Replace sidewalks as necessary.

• Replace and upgrade site lighting.

 

Start Design: Complete

Start Construction: Complete

Final Completion:  Complete

 

Birmingham Falls Elementary School – (2009)

 

Cogburn Woods Elementary School

Renovation and modification of existing building which may include the following:

• Provide waterproof wall finish in K-1 as required.

• Replace floor finishes as needed.

• Painting as needed.

• Provide fly fan at kitchen entrance door.

 

Start Design:Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Fall 2017

 

Crabapple Crossing Elementary School

Major renovation and modification of existing building and site improvements which may include the following work:

• Replace as needed marker/tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replacement of floor finishes as needed.

• Replacement of hard floor and wall tile as necessary.

• Replace and/or refinish stage wood flooring.

• Replace acoustical ceiling grid and tile as required.

• Painting as necessary.

• Replace roofing.

• Replace and/or repair plumbing fixtures as required.

• Major HVAC upgrade and replacement.

• Provide exhaust system for art room kiln.

• Revise electrical service at kitchen and serving line equipment as needed.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Replace sidewalks as necessary.

• Replace and upgrade site lighting.

 

Start Design: Complete

Start Construction:  Summer 2015

Final Completion: Summer 2016

 

Summit Hill Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replace floor finishes as needed.

• Painting as necessary.

• Update intercom and sound systems as required.

• Update fire alarm system as required.

• Update security system as required.

• Provide fly fan at kitchen’s entrance.

• Energy conservation improvements as needed.

 

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: Summer 2017

 

* Additional work at each campus may also include the following improvements as needed: furniture and equipment replacement, visitor identification equipment, access control upgrades and surveillance equipment. Other improvements associated with the integration of system wide technology standards, educational specifications and design requirements may also be included per Fulton County Schools’ Board policy.

** Note 1 - Floor covering replacements for elementary school gymnasiums is complete.

***Note 2 – Elementary school play equipment replacement is presently under construction.