Johns Creek High School – (2009)

 

Autrey Mill Middle School

Classroom addition to increase school capacity by eleven (11) instructional units.

Renovation and modification of existing buildings and site improvements which may include the following:

• Upgrade building’s security system as necessary.

• Patch, repair or replace tennis courts surface.

 

Start Design: Complete

Start Construction: In Process

Final Completion: Summer 2016

 

Barnwell Elementary School

Major renovation and modification of existing building and site improvements which may include the following work:

• Major HVAC replacement and upgrade.

• Replacement of floor finishes as required.

• Replace gymnasium flooring surface (Note 1)

• Replace as needed marker/ tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Painting as necessary.

• Replace acoustical ceiling grid and tile as required.

• Provide exhaust system for art room kilns.

• Update public address and sound system as required.

• Update security system as required.

• Replace fire alarm system and devices as required.

• Replace lighting fixtures as necessary.

• Replace plumbing fixtures as required.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Energy conservation improvements as needed.

Start Design: Complete

Start Construction: Complete

Final Completion:  Complete

 

Dolvin Elementary School

Major renovation and modification of existing building and site improvements which may include the following work:

• Replacement and/or repair of selected doors and hardware.

• Replacement of floor finishes as needed.

• Painting as necessary.

• Replace as needed marker/tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replace acoustical ceiling grid and tile as required.

• Major HVAC upgrade and replacement.

• Upgrade fire protection sprinkler system as required.

• Update building’s electrical systems as required.

• Replace selected light fixtures in ceiling grid.

• Replace and/or repair domestic water piping, sanitary sewer system and plumbing fixtures as required.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots as required.

• Replace sidewalks as necessary.

Start Design: Complete

Start Construction:  In Process

Final Completion:  No Later Than Fall 2015

 

Medlock Bridge Elementary School

Major renovation and modification of existing building and site improvements which may include the following work:

• Replace as needed marker and tack boards, toilet accessories, toilet partitions and shelving.

• Replace classroom cabinets and countertops as necessary.

• Replacement of floor finishes as needed.

• Replace acoustical ceiling grid and tile as required.

• Provide painting as necessary.

• Replace roofing at flat areas.

• Replace and/or repair plumbing fixtures as required.

• Major HVAC system replacement.

• Add air conditioning and replace exhaust hood at kitchen.

• Provide exhaust system for art room kilns.

• Replace kitchen’s exhaust hood and fans.

• Replace selected light fixtures in ceiling grid.

• Replace emergency generator.

• Revise electrical service to kitchen and serving line equipment as needed.

• Add fly fan at kitchen’s entrance.

• Energy conservation improvements as needed.

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Fall 2017

 

* Additional work at each campus may also include the following improvements as needed: furniture and equipment replacement, visitor identification equipment, access control upgrades and surveillance equipment. Other improvements associated with the integration of system wide technology standards, educational specifications and design requirements may also be included per Fulton County Schools’ Board policy.

** Note 1 - Floor covering replacements for elementary school gymnasium is complete.

***Note 2 – Elementary school play equipment replacement is presently under construction.