Chattahoochee Cluster Improvements

 

 

 

 

 

 

Chattahoochee High School

Major building renovation and modification of existing building and site improvement which may include the following work:

• Replace as needed marker and tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replace as needed fixed furniture such as cabinets, countertops, blinds and fixed seating.

• Replacement of floor finishes as needed.

• Painting as needed.

• Replace acoustical ceiling grid and tile as required.

• Replace domestic water heaters and electric water coolers as required.

• Major HVAC upgrade and replacement.

• Replace emergency generator.

• Update intercom and sound systems as required.

• Replace fire alarm system and devices as required.

• Update security system as required.

• Upgrade elevator controls.

• Replace and/or refinish stage wood flooring.

• Revise electrical service to kitchen and serving line equipment.

• Reconfigure kitchen and dining room for additional serving lines.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Replace sidewalks and pedestrian pavement as necessary.

 

Start Design: Complete

Start Construction:  In Progress

Final Completion: No Later Than Fall 2015

 

Taylor Road Middle School

New classroom addition increasing school capacity by eight (8) instruction units.

Major building renovation and modification of existing building and site improvement which may include the following work:

• Patch and repair of exterior walls.

• Provide painting as needed.

• Replace as needed marker and tack boards, lockers, toilet accessories, toilet partitions and shelving.

• Replace as needed fixed furniture such as cabinets, countertops, blinds and fixed seating.

• Replacement of floor finishes as needed.

• Replace acoustical ceiling grid and tile as required.

• Replace and/or repair plumbing fixtures, including water coolers as required.

• Major HVAC upgrade and replacement.

• Provide exhaust system for art room kilns.

• Replace emergency generator.

• Update security system as required.

• Expand and renovate kitchen.

• Revise electrical service to kitchen and serving line equipment as needed.

• Energy conservation improvements as needed.

• Add stage platform in gymnasium.

• Upgrade site lighting.

• Repair and/or replace tennis courts surface.

• Repair and/or replace running track surface

 

Start Design: Complete

Start Construction: In Process

Final Completion: Fall 2016 

 

Abbotts Hill Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement of floor finishes as required.

• Painting as needed.

• Replace gymnasium flooring surface. (Note 1)

• Additional kitchen equipment as needed.

• Energy conservation improvements as needed.

• Repair, resurface and restripe parking lots and entrance drives as required.

• Investigate and repair site erosion control issues.

 

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Summer 2017

 

Ocee Elementary School

Renovation and modification of existing buildings and site improvements which may include the following:

• Replacement of floor finishes as needed.

• Painting as needed.

• Energy conservation improvements as needed.

 

 Start Design: Winter 2015 

Start Construction: Summer 2016

Final Completion: No Later Than Fall 2017

 

State Bridge Crossing Elementary School

Major building renovation and modification of existing building and site improvements which may include the following work:

• Replacement of floor finishes as needed.

• Replace gymnasium flooring surface. (Note 1)

• Painting as necessary.

• Major HVAC upgrade and replacement.

• Replace emergency generator.

• Update intercom and sound systems as required.

• Update fire alarm system as required.

• Update security system as required.

• Revise/replace lighting as needed.

• Revise electrical service to kitchen and serving line equipment as needed.

• Add fly fan at kitchen’s entrance door.

 

Start Design: Winter 2015

Start Construction: Summer 2016

Final Completion: No Later Than Summer 2017

 

* Additional work at each campus may also include the following improvements as needed: furniture and equipment replacement, visitor identification equipment, access control upgrades and surveillance equipment. Other improvements associated with the integration of system wide technology standards, educational specifications and design requirements may also be included per Fulton County Schools’ Board policy.

** Note 1 - Floor covering replacements for elementary school gymnasiums is complete.

***Note 2 – Elementary school play equipment replacement is presently under construction.