Alpharetta Cluster Improvements

 
 
 
 
 
 

 

 

 

 

 

 

 

 

Alpharetta High School

• Renovation and modification of existing buildings and site improvements which may include the following:

  • Replacement of floor finishes as required, including auditorium.
  • Provide upgrade to exhaust system for Art Room kilns.
  • Improve exhaust systems in building’s toilets.
  • Upgrade science rooms exhaust system.
  • Painting as needed.
  • Replace fire alarm panel and devices as required.
  • Replace controls on elevators.
  • Replace and upgrade site lighting.
  • Repair and/or modify site drainage issues.
  • Replace/repair track surface.
Start Design:  Spring 2016
Start Construction:  Summer 2017
Final Completion: No Later Than Fall 2017
 

 

 

Webb Bridge Middle School

• Renovation and modification of existing buildings and site improvements which may include the following:

  • Update fire alarm, intercom and sound systems.
  • Painting as needed.
  • Update security system as required.
  • Replace floor finishes as needed.
  • Revise electrical service to kitchen and serving line equipment as needed.
  • Energy conservation improvements as needed.
  • Repair, resurface and restripe parking lots and entrance drives as required.
  • Replace and/or repair perimeter fencing around site.
  • Replace sidewalks as necessary.
Start Design: Winter 2015
Start Construction: Summer 2016
Final Completion:  Fall 2017

 

 

Creek View Elementary School

• Classroom addition increasing school capacity by ten (10) instructional units and associated site improvements.
• Renovation and modification of existing buildings and site improvements which may include the following:

  • Patch and repair interior wall cracks.

  • Replacement of floor finishes as needed.

  • Painting as needed.

  • Add fly fan at kitchen entrance.

Start Design: Project is on Hold
Start Construction: TBD
Final Completion: TBD

 

Lake Windward Elementary School

• Major renovation and modification of existing building and site improvements which may include the following:

  • Replace as needed marker and tack boards, lockers, toilet accessories, toilet partitions and shelving.

  • Painting as necessary.

  • Replacement of floor finishes as needed.

  • Replace acoustical ceiling grid and tile as required.

  • Major HVAC upgrade and replacement.

  • Update intercom and sound systems as required.

  • Update fire alarm system as required.

  • Update security system as required.

  • Revise electrical service to kitchen and serving line equipment as needed.

  • Energy conservation improvements as needed.

  • Resurface and repair play court.

 

Start Design: In Progress
Start Construction: Summer 2015
Final Completion: No Later Than Fall 2016

 

 

Manning Oaks Elementary School

• Renovation and modification of existing buildings and site improvements which may include the following:

  • Replacement of floor finishes as needed.

  • Add moisture resistant wall finish in K-1 restrooms.

  • Update building’s mechanical exhaust system in the toilets as required.

  • Painting as needed.

  • Repair and/or replace roof.

  • Revise electrical service to kitchen and serving line equipment as needed.

  • Add fly fan at kitchen’s entrance.

  • Energy conservation improvements as needed.

  • Replace sidewalks as necessary.

  • Upgrade site lighting.

 

Start Design: Winter 2015
Start Construction: Summer 2016
Final Completion: No Later Than Fall 2017

 

New Prospect Elementary School

• Renovation and modification of existing buildings and site improvements which may include the following:

  • Replacement of floor finishes as needed.
  • Replace as needed marker and tack boards, toilet accessories, toilet partitions and shelving.
  • Update building’s HVAC system and controls as required.
  • Provide painting as necessary.
  • Replace emergency generator.
  • Update intercom and sound systems as required.
  • Update building’s fire alarm system as required.
  • Update security system as required.
  • Revise electrical service to kitchen and serving line equipment as needed.
  • Add fly fan at kitchen’s entrance.
  • Add air conditioning and replace exhaust hood in kitchen.
  • Energy conservation improvements as needed.
  • Repair, resurface and restripe parking lots and entrance drives as required.
  • Add site security lighting as necessary.
 
Start Design:  Winter 2015
Start Construction: Summer 2016
Final Completion: No Later Than Fall 2017


* Additional work at each campus may also include the following improvements as needed: furniture and equipment replacement, visitor identification equipment, access control upgrades and surveillance equipment. Other improvements associated with the integration of system wide technology standards, educational specifications and design requirements may also be included per Fulton County Schools’ Board policy.

** Note 1 - Elementary schools' gym floor covering replacements have been completed.

***Note 2 – Elementary school play equipment is presently being installed at selected schools.